Earned Value Analysis

A given project has a BAC = $20,000, AC(cumulative to date) = $12,500, and EV(cumulative to date) = $12,700. Using CPI as a basis for future cost efficiency, what is the ETC? A) $7,000 B) $7,185 C) $7,556 D) $8,000
The post Earned Value Analysis appeared first on Class Assignments Help.
Earned Value Analysis was first posted on September 27, 2022 at 6:31 am.©2019 "Class Assignments Help". Use of this feed is for personal non-commercial use only. If you are not reading this article in your feed reader, then the site is guilty of copyright infringement. Please contact me at [email protected]